3-28. TENSION LOAD CELL REPLACEMENT
THIS TASK COVERS:
a. Removal
b. Installation
INITIAL SETUP
Tools
Tool Kit, General Mechanics
(Item 67, Appendix F)
Materials/Parts
Sealing compound (Item 29, Appendix B)
Lockwasher (Item 66, Appendix E)
Personnel Required
1 Assistant
Equipment Condition
FRS unloaded, mast and boom in raised
position, (TM 9-4940-568-10).
a.
Removal
NOTE
Tag and mark all hoses and
electrical connectors prior to
disconnecting.
Plug all hoses after removal to
prevent dirt from entering
hydraulic system.
Remove cable ties as required.
(1) Disconnect tension load cell connector
(1) from overload shutdown box (2).
(2) Disconnect proximity sensor connector
(3) from overload shutdown box (2).