Figure 26. Right Starter Cable P-clamp Beneath Hydraulic Oil Supply Tube.
Figure 28. Right Starter Cable P-clamp at Frame by Junction Block.

Field Maintenance Manual For Military 621G Scraper -5 Page Navigation
  270    271    272    273    274  275  276    277    278    279    280  
img
.
TM 5-3805-296-23-5
0310
RIGHT STARTER POSITIVE CABLE INSTALLATION CONTINUED
NOTE
Route cable as noted during removal.
Install electrical connections as noted during removal.
9. Install right starter cable (Figure 27, Item 3) on junction block terminal (Figure 27, Item 1).
10. Install washer (Figure 27, Item 2) and nut (Figure 27, Item 5) on junction block terminal (Figure 27, Item 1).
11. Position cover (Figure 27, Item 4) on junction block terminal (Figure 27, Item 1).
Figure 27. Right Starter Cable at Junction Block.
0310
0310-28