1. Position hydraulic line (Figure 14, Item 1) on machine.
2. Install hydraulic line (Figure 14, Item 1), two washers (Figure 14, Item 7), and bolts (Figure 14, Item 14) on
bracket (Figure 14, Item 8).
3. Install new O-ring (Figure 14, Item 13) on hydraulic hose (Figure 14, Item 12).
4. Install hydraulic hose (Figure 14, Item 12), two flange halves (Figure 14, Item 9), four washers,
(Figure 14, Item 10), and bolts (Figure 14, Item 11) on hydraulic line (Figure 14, Item 1).
5. Install new O-ring (Figure 14, Item 5) on hydraulic line (Figure 14, Item 6).
6. Install hydraulic line (Figure 14, Item 6), two flange halves (Figure 14, Item 2), four washers (Figure 14, Item 3),
and bolts (Figure 14, Item 4) on hydraulic line (Figure 14, Item 1).