TM 5-3805-296-23-2
0090
Table 1. 1775 Implement Pump Pressure Calibration Switch Diagnostic Codes Continued.
090
CID FMI
TEST OR INSPECTION
CORRECTIVE ACTION
Test Step 2. Test for Shorted
1775-04 Implement Pump
Transmission Wiring Harness.
1. Turn ignition switch and battery
Voltage Below Normal
disconnect switch to OFF position
Continued
(TM 5-3805-296-10).
2. Disconnect connector A-C1
(WP 0012, Figure 106) from
connector J-C3 (WP 0012,
Figure 101).
Continuity Replace transmission
(WP 0540), test for continuity
wiring harness (WP 0266).
between connector A-C1
Proceed to Test Step 5.
terminal 6 (WP 0012, Figure 106)
No Continuity Proceed to step 4.
and all other terminals in
connector A-C1 (WP 0012,
Figure 106).
Continuity Replace transmission
(WP 0540), test for continuity
wiring harness (WP 0266).
between connector A-C1
Proceed to Test Step 5.
terminal 6 (WP 0012, Figure 106)
No Continuity Proceed to step 5.
and ground.
Continuity Replace transmission
(WP 0540), test for continuity
wiring harness (WP 0266).
between connector A-C1
Proceed to Test Step 5.
terminal 14 (WP 0012, Figure 106)
No Continuity Proceed to step 6.
and all other terminals in
connector A-C1 (WP 0012,
Figure 106).
Continuity Replace transmission
(WP 0540), test for continuity
wiring harness (WP 0266).
between connector A-C1
Proceed to Test Step 5.
terminal 14 (WP 0012, Figure 106)
No Continuity Proceed to Test
and ground.
Step 3.
Test Step 3. Test for Shorted Chassis
Wiring Harness.
1. Disconnect connector J-C8
(WP 0012, Figure 100) from
connector W-C1 (WP 0012,
Figure 99).
Continuity Replace chassis wiring
(WP 0540), test for continuity
harness (WP 0305).
between connector J-C3 terminal 6
Proceed to Test Step 5.
(WP 0012, Figure 101) and all
No Continuity Proceed to step 3.
other terminals in connector J-C3
(WP 0012, Figure 101).
0090-7