TM 9-2610-200-14
2-44
CHAPTER 2. CARE, MAINTENANCE, AND INSPECTION (Con't)
SECTION III. UNIT MAINTENANCE (Con't)
2-29. RUNFLAT TIRE MAINTENANCE (HMMWV) (Con't).
c. ASSEMBLY (Con't)
3. Install two runflat halves (11) inside tire (6), ensuring that notches are aligned on same side of runflat
halves.
4. Secure runflat halves (11) together with four flange bolts (10) and
new self-locking nuts (12). Using torque wrench adapter, torque self-
locking nuts to 18-22 Ib-ft. (24-30 N.m).
5. Lubricate new preformed packing (7) with tire and rim lubricant and
install preformed packing on first ledge of rim half (8). Ensure that
preformed packing is not twisted and is uniformly positioned 1 inch (2.5
cm) below studs (9). Do not overstretch preformed packing.