TM 5-3805-296-23-6
0381
REMOVAL CONTINUED
Figure 3. Ground Level Shutdown Switch.
0381
END OF TASK
CLEANING AND INSPECTION
000381
Clean and inspect all components IAW Electrical General Maintenance Instructions (WP 0540).
END OF TASK
INSTALLATION
000381
NOTE
Install wiring harness connector as noted during removal.
Install tiedowns as noted during removal.
1. Install bracket (Figure 3, Item 5) on ground level shutdown switch connector (Figure 3, Item 7).
2.
Position ground level shutdown switch (Figure 3, Item 9) on machine and connect machine harness connector
(Figure 3, Item 6) to ground level shutdown switch harness (Figure 3, Item 2).
3. Install bracket (Figure 3, Item 5), ladder clip (Figure 3, Item 3), washer (Figure 3, Item 8), and bolt
(Figure 3, Item 4) on machine.
4. Install new tiedown strap (Figure 3, Item 1) on ground level shutdown switch harness (Figure 3, Item 2) and
ladder clip (Figure 3, Item 3).
5. Install ground level shutdown switch cover (Figure 2, Item 2) and nut (Figure 2, Item 1) on ground level
shutdown switch (Figure 2, Item 3).
6. Lower ground level shutdown switch cover (Figure 2, Item 2).