TM 9-4940-568-34
3-93
(3) Install two preformed packings (9) and
connect adapters (8) to fittings (10).
(4) Apply sealing compound to threads of
two screws (1).
(5) Install bracket (3) on hoist assembly (7)
with two washers (2) and screws (1).
(6) Install preformed packing (5) and
connect adapter (4) to check valve (6).
END OF TASK
Follow-On Maintenance
Install tension load cell
(para 3-28).
Install hoist cable
(para 5-5).
Check crane for proper
operation and hydraulic
leaks, (TM 9-4940-568-10).
Load test crane
(para 3-5).
1, 2
3
7
4, 5, 6