TM 9-4940-568-34
3-95
NOTE
Tag connectors and connection
points prior to disconnecting.
(2) Disconnect three connectors (3) from
overload shutdown box (4).
(3) Remove four screws (5), lockwashers
(6), flat washers (7), grounding strap (8),
four nylon washers (9), and overload
shutdown box (4) from boom assembly
(10). Discard lockwashers.
b. Installation
(1) Install overload shutdown box (4) on
boom assembly (10) with four nylon
washers (9), ground strap (8), four flat
washers (7), lockwashers (6) and
screws (5).
(2) Connect
three connectors (3) to
overload shutdown box (4).
(3) Connect cable eye (1) to screw (2).
END OF TASK
Follow-On Maintenance
Check crane for proper
operation and hydraulic
leaks.
Load test crane
(para 3-5).