2-29. MATERIAL HANDLING CRANE (MHC) OPERATION (CONT).
d.
Deploying Outrigger and Jack Cylinders.
13
9
20
14
14
12
10
11
Ensure area is clear on both sides of crane before extending outrigger jacks. Failure to
comply may result in injury to personnel or damage to equipment.
Keep hands and feet clear of outriggers during operation. Failure to comply may result in
injury to personnel.
(1)
Open outrigger control cover (9).
NOTE
Ensure chain of pin is looped over top of outrigger latch.
(2)
Remove pin (10) and retaining pin (11) and place left outrigger latch (12) in open position. Install
retaining pin and pin.
(3)
Repeat Step (2) for right outrigger latch.
(4)
Move O/R EXT lever (13) to OUT position until outriggers (14) are fully extended.