TM 9-4940-568-34
3-69
(11) Install two preformed packings (16 and
17) on plugs (14 and 15).
(12) Install two plugs (14 and 15) in holding
valve (5).
(13) Install two preformed packings (13 and
12) on two fittings (10 and 11).
(14) Install fittings (10 and 11) in holding
valve (5).
(15) Connect two hoses (8 and 9) to fittings
(10 and 11).
(16) Install preformed packings (7 and 6) on
fitting (4).
(17) Install fitting (4) on holding valve (5).
(18) Connect hose (3) to fitting (4).
NOTE
Step (19) applies only to RH lift
cylinder.
(19) Connect overload lockout connector (1)
to overload shutdown assembly (2).
END OF TASK
Follow-On Maintenance
Lubricate lift cylinder
(TM 9-4940-568-10).
Check crane for proper
operation and hydraulic
leak (TM 9-4940-568-10).
Load test crane
(para 3-5).