TM 5-3805-296-23-6
0429
REMOVAL CONTINUED
1. Remove four bolts (Figure 8, Item 6), washers (Figure 8, Item 5) two flange halves (Figure 8, Item 4),
and hydraulic line (Figure 8, Item 2) from hydraulic line (Figure 8, Item 1).
2. Remove O-ring (Figure 8, Item 3) from hydraulic line (Figure 8, Item 2). Discard O-ring.
3. Remove four bolts (Figure 7, Item 8), washers (Figure 7, Item 9), two flange halves (Figure 7, Item 10), and
hydraulic line (Figure 7, Item 7) from hydraulic line (Figure 7, Item 2).
4. Remove two bolts (Figure 8, Item 13), washers (Figure 8, Item 14), clamp (Figure 8, Item 12), and hydraulic
line (Figure 8, Item 2) from hitch.
5. Remove O-ring (Figure 8, Item 11) from hydraulic line (Figure 8, Item 2). Discard O-ring.
6. Remove hydraulic line (Figure 8, Item 2) from machine.
Figure 8. Right Line.
0429
END OF TASK