TM 5-3805-296-23-6
0419
INSTALLATION CONTINUED
13. Install new O-ring (Figure 18, Item 3) on hydraulic hose (Figure 18, Item 4).
14. With assistance, install hydraulic hose (Figure 18, Item 4), two flange halves (Figure 18, Item 5), four washers
(Figure 18, Item 1), and bolts (Figure 18, Item 2) on spacer (Figure 18, Item 6).
Figure 18. Main Control Valve Connection.
0419
END OF TASK
FOLLOW-ON TASKS
000419
Verify correct operation of machine (TM 5-3805-296-10).
END OF TASK
END OF WORK PACKAGE