TM 5-3805-296-23-5
0347
INSTALLATION CONTINUED
NOTE
Install P-clamp as noted during removal.
Install wiring harness as tagged and marked during removal.
18. Install wiring harness insulation (Figure 22, Item 5) on wiring harness (Figure 22, Item 6).
19. Install identification tag (Figure 22, Item 4) on wiring harness insulation (Figure 22, Item 5).
20. Install P-clamp (Figure 22, Item 3) on wiring harness insulation (Figure 22, Item 5).
21. Connect wiring harness connector (Figure 22, Item 2) to fuel sending unit connector (Figure 22, Item 1).
22. Install P-clamp (Figure 22, Item 3), washer (Figure 22, Item 8), and bolt (Figure 22, Item 7) on machine.
Figure 22. P-clamp and Wiring Harness Insulation Near Fuel Sending Unit.
0347